Khudi Hydropower Project is a run-of-river small hydropower scheme with gross head of 103 m designed for an installed capacity of 4 MW with two generating units. Headworks consist of boulder lined weir, intake, under sluice, approach canal, desilting basin and forebay. Waterway consists of about 2.5 km long exposed steel penstock pipe of 1.75 m diameter from headworks to powerhouse with Inverted Syphone across the Khudi River.

Project Khudi Hydropower Project
Location Lamjung District, Khudi/Ghana Pokhara VDC
Owner Khudi Hydropower Ltd.
Engineer Butwal Power Company Hydroconsult (BPCH)
Capacity 4 MW
Settling Basin 2 chambers 70 m x 11.6 m x 5.17 m
Powerhouse Surface
Turbine Francis 2 x 2 MW
Cost of Civil Work NRs. 164 Million